Bitcoin mining firm HIVE Digital Technologies is setting its sights on a lucrative new revenue stream, targeting $45 million in annual income from a high-performance artificial intelligence data center located in Sweden. However, despite the ambitious projections and months of ongoing discussions, the publicly traded crypto miner has yet to ink a final, definitive lease agreement for the property.
In its latest quarterly earnings update, HIVE reiterated that its 32-megawatt Big Boden facility could soon generate substantial yearly revenue through a long-term colocation arrangement. Company leadership has been transparent about the hurdles remaining before those financial projections become a reality. Realizing the projected $45 million hinges entirely on several crucial milestones, including the execution of a definitive agreement, securing comprehensive project financing, completing necessary facility upgrades, and successfully bringing the modernized data center into commercial service.
The proposed venture first came to light in June, when HIVE initially disclosed the high-stakes proposal to the public. The blueprint involves an unnamed, investment-grade Swedish technology company and contemplates a multi-year lease lasting up to a decade. During the company’s recent earnings call, CEO Aydin Kilic provided an update on the state of the negotiations, explaining that the two parties are currently working through complex commercial terms. Specifically, the talks center around financial deposits, termination rights, and various other contractual provisions that could ultimately influence the project’s overall financing costs. Demonstrating forward momentum, Kilic noted that a lender’s consultant had visited the Boden site the week prior to inspect the facilities and evaluate the technical readiness of the infrastructure.
"We do not want to rush into a deal just for the sake of reporting new top-line revenue," Kilic told stakeholders and analysts during the earnings call, emphasizing a cautious and deliberate approach to corporate growth and risk management.
Once a definitive lease is formally secured, HIVE expects to actively pursue project financing for the Boden development, with corporate bonds emerging as a potential avenue to fund the endeavor. At present, the company has not announced a definitive completion date for the ongoing negotiations, leaving the timeline for the final agreement open-ended as both sides carefully vet the legal and financial terms.
From Crypto Mining to AI Infrastructure

Transforming the Big Boden site into a cutting-edge artificial intelligence installation will require a substantial physical and technical overhaul. The existing data center must undergo a major makeover to support modern high-density computing demands. HIVE’s current plans involve retrofitting the facility to house up to 10,000 Nvidia GB300 GPUs. Because these advanced graphics processing units generate immense amounts of heat and require specialized environmental controls, the infrastructure upgrade will heavily feature advanced liquid cooling systems capable of managing high-density computing racks efficiently.
Although the existing utility connection at the Boden site provides 32 megawatts of total power, the proposed anchor customer would utilize approximately 25 megawatts of usable computing capacity. The remaining power allocation would be dedicated to supporting vital data center operations, cooling systems, and network redundancy.
The evolution of the Boden property reflects a broader, strategic pivot within the company’s business model. "This site has evolved from a GPU compute facility supporting Ethereum," Kilic noted earlier this year when describing the planned conversion into a more powerful, enterprise-grade AI installation.
This strategic expansion follows HIVE’s wider corporate effort to diversify its revenue streams and move beyond the traditional volatility of Bitcoin mining. That deliberate shift has already yielded several major high-performance computing and GPU-cloud contracts in recent months. Most notably, HIVE signed a landmark three-year AI computing agreement with Bell Canada and Cohere in June, a deal covering 2,304 Nvidia GPUs that further accelerated the company’s diversification away from pure-play cryptocurrency mining.
HIVE currently reports $185 million in contracted GPU-cloud annualized run-rate revenue. However, a significant portion of that figure remains forward-looking, as only $40 million is currently live and generating income. The remainder represents contracted capacity associated with projects that have not yet entered active service.
Looking further ahead, the company has established a lofty target of achieving approximately $700 million in total high-performance computing annualized revenue by the end of 2028. Company executives acknowledge that reaching this milestone will require additional capital, extensive construction, and sustained customer commitments across multiple upcoming infrastructure projects. For the immediate future, however, HIVE’s primary operational objective remains localized to Sweden, where the company’s next critical milestone is successfully securing the definitive lease for the Big Boden facility before moving forward with project financing and the intensive retrofit process.